Such view of the matter, this Court is of the view that as the dispute itself is not resolved by MSEF Council, only the matter has been referred to Arbitration with the consent of the parties, further the contract governing the parties also provides for such reference to arbitration, the second respondent has also already invoked the Arbitration Clause by issuing notice in the year 2013 itself and the petitioner has also participated in the said arbitration proceedings, now the petitioner cannot challenge the impugned order at this belated stage that to when the arbitration proceedings is in the final stage. Further, when the parties have consciously agreed to resolve the dispute arising out of the contract by way of arbitration, they can very well agitate their right before the Arbitrator and canvass their points and no prejudice would be caused to them since the Arbitrator has been independently appointed by the Arbitration Center of the Madras High Court. Such view of the matter, this Court finds no merit in this writ petition and the writ petition is liable to be dismissed and accordingly dismissed. Consequently, the connected miscellaneous petition is closed. No costs. 03.01.2023 Index : Yes / No Neutral Citation : Yes / No kk To The Chairman, Micro Small Enterprises Facilitation Council, Represented by its Regional Joint Director of Industries and Commerce, Thiru-vi-ka Industrial Estate, Guindy, Chennai – 600 032. The Hon’ble Presiding Arbitrator, Madras High Court Arbitration Centre, High Court, Parry’s Corner, George Town, Chennai – 600 108. N.SATHISH KUMAR, J. kk W.P.No.6216 of 2021 and W.M.P.No.6834 of 2021 03.01.2023

 

IN THE HIGH COURT OF JUDICATURE AT MADRAS

 

DATED: 03.01.2023

 

CORAM:

 

THE HONOURABLE MR.JUSTICE N.SATHISH KUMAR

 

W.P.No.6216 of 2021

and W.M.P.No.6834 of 2021

 

Bharat Heavy Electricals Limited,

Power Sector Western Region,

Represented by its General Manager

and Head Mr.Sanjeev Kumar Agarwal,

No.345, Kingsway, Nagpur – 440 001. .. Petitioner

 

Vs.

  1. The Chairman,

Micro Small Enterprises Facilitation Council,

Represented by its Regional Joint Director of

Industries and Commerce,

Thiru-vi-ka Industrial Estate,

Guindy, Chennai – 600 032.

 

  1. ICS Engineering Limited,

Represented by its Director,

No.144, Shaila Villa, Thomas Street,

Ganapathy Nagar, Alapakkam,

Porur, Chennai – 600 116.

Also at: No.3A, 3rd Floor, ‘Pushkar’,

‘Soundarya Enclave, Block No.H-65,

East Avenue Road, Periyar Nagar,

Korattur, Chennai – 600 080.

 

  1. The Hon’ble Presiding Arbitrator,

Madras High Court Arbitration Centre,

High Court, Parry’s Corner,

George Town, Chennai – 600 108. .. Respondents

Prayer : Writ Petition has been filed under Article 226 of the Constitution of India seeking a Writ of Certiorari calling for the records of the first respondent culminating in passing the order dated 09.06.2017 in O.P.No.MSEFC/CR/68/2016 and quash the same.

 

For Petitioner : Mr.V.V.Sivakumar

 

For Respondent 1 : Mr.N.Naveen Kumar

Government Advocate

 

For Respondent 2 : Mr.O.Padma Prakash

 

For Respondent 3 : No appearance

– – – – –

 

 

O R D E R

 

This writ petition has been filed challenging the order passed by the first respondent Micro Small Enterprises Facilitation Council, dated 09.06.2017 in O.P.No.MSEFC/CR/68/2016.

 

  1. The case of the writ petitioner is that the second respondent was the successful bidder in respect of a subcontract floated by the petitioner through its Western, Eastern and Northern regions. The contract is in respect of material handling, erection, testing and commissioning of boilers, turbines and their auxiliaries in the State of Gujarat, Orissa, Bihar and Rajasthan.

 

  1. The contracts are in the nature of works contract. The second respondent could not able to perform the contract as per the stipulations. In the meanwhile, the second respondent has approached the first respondent Micro Small Enterprises Facilitation Council (for short ‘MSEF Council’) seeking conciliation of difference of opinion which had arisen between the petitioner and the second respondent on the delay in execution of the subject contract.

 

  1. The MSEF Council by its impugned order dated 09.06.2017, concluded that conciliation process could not succeed as the matter involves intricate engineering issues of contract management i.e. deployment of machineries, labour etc.,. The MSEF Council has however referred the matter to the Arbitration Center of the Madras High Court. The writ petitioner has received communication from the Arbitration Center of Madras High Court after a lapse of three years.

 

  1. The petitioner appeared before the Arbitrator and agreed to the time schedule of hearing drawn up by the Arbitrator. Now, it is contended that MSEF Council has no jurisdiction to refer the issue to the Arbitrator since the dispute relates to works contract. The first respondent MSEF Council ought to have taken cognizance of these aspect of the matter and ought to have declined to refer the matter to arbitration and therefore on the ground of jurisdiction, the order of the first respondent MSEF Council is challenged in this writ petition.

 

  1. The second respondent has filed a counter stating that their company is a MSME unit engaged in the business of planning, fabrication, construction, erection and commissioning of plant, machinery etc. The second respondent satisfactorily completed the contract at Kutch site, Gujarat and was executing the contracts at the other sites without any hitch or room for any complaint.

 

  1. The second respondent has further stated that the writ petitioner has failed to pay the amount to the second respondent and therefore the second respondent has sent a letter to the petitioner for initiating arbitration in the year 2013 itself. As the steps taken by the second respondent did not fructified, finally he filed a reference to the MSEF Council.

 

  1. Before the MSEF Council, as conciliation has failed, with consent of both the parties, the matter has been referred to the Arbitration Center of the Madras High Court. An Arbitrator was also appointed by the Arbitration Center of the Madras High Court. The petitioner’s representative has appeared before the Arbitrator on the date of preliminary hearing along with the counsel for the petitioner. They also gave consent to the Arbitration and the time schedule fixed by the Arbitrator. Claim petition and written statement has also been filed. Therefore, having given consent for arbitration, now the impugned order cannot be challenged after a lapse of several years and seeks dismissal of the writ petition.

 

  1. The main contention of the learned counsel appearing for the petitioner is that a contract was entered for works contracts which has not been disputed by the other side. Such being the position, the learned MSEF Council should not have entertained the reference made by the second respondent and referred the matter to Arbitration.

 

  1. It is his further contention that when MSEF Council has no jurisdiction to entertain the dispute since it is a works contract, conducting conciliation and referring the matter to arbitration cannot be sustained in the eye of law. The impugned order proceeded as if the learned counsel for the petitioner has given his consent for referring the matter to the Arbitration Center of the Madras High Court to initiate the process of arbitration to resolve the issue. It is his contention that no such consent has been given by the learned counsel for the petitioner. At any event, merely based on the consent of the learned counsel for the petitioner, the MSEF Council ought not to have referred the matter to the Arbitrator since the MSEF Council has no jurisdiction to entertain the very dispute. Therefore, the reference made by MSEF Council itself is bad in the eye of law. In support of his submissions the learned counsel relied upon the following judgments:

(i) Samvit Buildcare Private Limited Vs. Ministry of Civil Aviation in Special Civil Application No.1094 of 2018, dated 12.03.2018;

(ii) Rashtriya Ispat Nigam Limited Vs. Union of India in W.P.Nos.27670 of 2021 dated 26.04.2022;

(iii) Kerala State Electricity Board Vs. Kurien E.Kalathil reported in (2018) 4 SCC 793;

(iv) Surya International Vs. Union of India reported in Spl.C.A.No.14297 of 2017 dated 15.11.2017; and

(v) Sterling and Wilson Private Limited Vs. Union of India reported in AIR 2017 Bom 242.

 

  1. Whereas, the learned counsel appearing for the second respondent would submit that admittedly there is an arbitration clause in the contract itself. The second respondent has in fact requested the petitioner to invoke Arbitration by sending a notice in the year 2013 itself. Even after such notice, the petitioner has not appointed any Arbitrator and dragged the matter one way or the other. Therefore, the second respondent has no other go except to file a claim before the MSEF Council for recovery of the money. The MSEF Council has in fact conducted conciliation and as the conciliation did not yield any result, the MSEF Council referred the matter to Arbitration Center of the Madras High Court for appointing an Arbitrator with the consent of the petitioner. Thereafter, an Arbitrator has been appointed by the Arbitration Center of the Madras High Court. Even before the Arbitrator, the petitioner has never raised any objections for his appointment or schedule of dates fixed by the Arbitrator. The learned counsel further submitted that arbitration proceedings has almost been completed and the second respondent side evidence is already over and on the petitioner’s side three witnesses were already examined and only one witness has to be examined on petitioner’s side.

 

  1. According to the learned counsel appearing for the second respondent, at this stage, the writ petition has been filed to quash the very impugned order, therefore the learned counsel for the second respondent submitted that even assuming that the MSEF Council has no jurisdiction to go into the complicated works contract, the fact remains that MSEF Council has not decided the issue whereas the MSEF Council has only referred the matter to the Arbitration Center of the Madras High Court with the consent of both the parties and that the appointment of the Arbitrator has also not been challenged by the petitioner and the petitioner has in fact participated in the arbitration proceedings and therefore now the petitioner cannot question the impugned order. Hence, the learned counsel appearing for the second respondent oppose this writ petition. In support of his submissions, he relied upon the following judgments:

(i) Krishna Bahadur Vs. M/s. Purna Theatre reported in MANU/SC/0667/2004;

(ii) Joint Action Committee of Airlines Pilots Association of India Vs. The Director General of Civil Aviation reported in AIR 2011 SC 2220;

(iii) State of Punjab Vs. Dhanjit Singh Sandhu reported in AIR 2014 SC 2004; and

(iv) The Rajasthan State Industrial Development and Investment Corporation Vs. Diamond and Gem Development Corporation Ltd reported in AIR 2013 SC 12241.

 

  1. I have heard the learned counsel on either side and also perused the materials available on record carefully.

 

  1. It is not disputed by both sides that the contract entered into between the petitioner and the second respondent provides for arbitration. Similarly, the second respondent has also sent a notice on 07.08.2013 for appointment of an Arbitrator as per Clause 2.14 of the General Conditions of Contract for Work in Construction Management of Bharat Heavy Electricals Limited. However, as the petitioner has not taken any steps for appointing an Arbitrator as per the Contract, claim has been filed by the second respondent before the MSEF Council for recovery of certain dues.

 

  1. It is relevant to note that in this writ petition the impugned order dated 09.06.2017, passed by the MSEF Council is challenged. A perusal of the impugned order makes it clear that after entertaining the reference, the MSEF Council meeting was held on 23.11.2016. Thereafter, conciliation has failed and it is recorded that since the matter involves intricate engineering issues of contract management, deployment of machineries, labour etc., arbitration by a professional body is needed and accordingly, with the consent of both sides the matter has been referred to Arbitration Center of the Madras High Court for appointment of Arbitrator. The impugned order clearly records in paragraph 5 as follows:

“5…….Accordingly, both sides agreed for nomination of Madras High Court Arbitration Centre for the arbitration process to resolve the issue.”

 

  1. Pursuant to the same, a communication has been sent by the Arbitration Center of the Madras High Court with some delay. It is relevant to note that the reference was made by the MSEF Council in the year 2017 itself to the Arbitration Center of Madras High Court, however due to some delay communication was sent from the Arbitration Center of Madras High Court only on 09.11.2020.

 

  1. Be that as it may, the Arbitration Center of the Madras High Court appointed Mr.K.M.Aasim Shehzad, Advocate as the Sole Arbitrator. The minutes of the first sitting held at 11.00 a.m. on 21.12.2020 before the Sole Arbitrator indicate that none of the parties and their respective counsel expressed any objections to the constitution of the present Arbitral Tribunal or objections as to the Arbitration Clause or the adjudication of the mater by the Tribunal. Pursuant to the same, the Arbitral proceedings were commenced. Now it is admitted by both sides that on the side of the claimant namely the second respondent herein his evidence has been closed and on the side of the writ petitioner three witnesses have already been examined and only one witness has to be examined. The above facts are not in dispute.

 

  1. It is relevant to note that it is the contention of the learned counsel appearing for the petitioner that though he has not given its consent before the MSEF Council, the Council had referred the matter to Arbitration. The fact remains that MSEF Council has recorded a fact that the matter has been referred to the Arbitration Center of the Madras High Court only after consent by both sides. That apart, before the Arbitrator also no objections whatsoever has been raised by the petitioner.

 

  1. It is relevant to note that the arbitration proceedings is in the final stage and even the application filed under Section 16 of the Arbitration and Conciliation Act, raising objections has been rejected by the Arbitrator. Now the writ petition has been filed for challenging the very impugned order on the ground that there is no jurisdiction for the MSEF Council to refer the matter to the Arbitrator on the ground that the contract is a works contract and therefore the MSEF Council cannot have any jurisdiction.

 

  1. Admittedly, the Contract governing the parties contains Arbitration Clause which is not in dispute. Clause 2.14 of the General Conditions of the Contract provides mechanism for the parties if they choose so to go for arbitration and the parties have agreed by way of contract for such resolution of dispute by Arbitrator. This Court is of the view that when the matter has been referred by the MSEF Council after consent of the parties to the Arbitration Center of the Madras High Court to nominate an Arbitrator, the same cannot be said to be without any jurisdiction, since the contract itself provides for arbitration when the parties have given consent for going to arbitration. After the proceedings before the Arbitrator has reached the final stage, the writ petitioner cannot take a U-turn and question the proceedings on the ground of jurisdiction. Once the petitioner has given his consent and has also participated in the proceedings, now he cannot take up the issue of jurisdiction. Though it is stated that since it is a works contract, the MSEF Council ought not to have entertained the reference, it is relevant to note that MSEF Council has not decided the issues arising out of the works contract. The MSEF Council has only referred the matter to the arbitration with the consent of the parties. Admittedly, the contract between the parties also provides for arbitration. Such view of the matter, this Court is of the view that having participated in the arbitration proceedings and now it is in the final stage, the writ petitioner cannot at this stage question the impugned order.

 

  1. The learned counsel appearing for the petitioner placed relied on a Division Bench judgment of the High Court of Gujarat in Samvit Buildcare Private Limited Vs. Ministry of Civil Aviation in Special Civil Application No.1094 of 2018, dated 12.03.2018, wherein the Division Bench has held that the contract in question is a works contract, for which the MSME Act shall not be applicable and that the authority is justified in applying QCBS method while evaluating bids and the eligibility criteria cannot be said to be perverse and/or arbitrary and accordingly dismissed the said writ petition. In the above matter, the writ petition has been filed for direction directing the respondents to accept the bids submitted by the petitioner considering Section 11 of the MSME Act and the Court rejected the said plea.

 

  1. The learned counsel appearing for the petitioner further relied upon a judgment of the Andhra Pradesh High Court in Rashtriya Ispat Nigam Limited Vs. Union of India in W.P.Nos.27670 of 2021 dated 26.04.2022. The Andhra Pradesh High Court has held that MSME Act is not applicable to the works contract. In the above judgment the learned Single Judge has also held that once a party appears before the Court or a Tribunal and raises an issue about the jurisdiction of the said Tribunal, it cannot be said that they have submitted to its jurisdiction. They are appearing under protest. Therefore, they are at liberty to seek an adjudication of this issue before the Writ Court under Article 226 of the Constitution of India. It is relevant to note that in the above judgment the jurisdiction of MSEF Council is questioned by the writ petitioner therein, whereas the impugned order in this writ petition does not show any such objections being raised as to its jurisdiction. Be that as it may, the MSEF Council has not involved itself in deciding the issue arisen out of the so called works contract. It has only referred the matter to the Arbitrator with the consent of the parties. Admittedly the parties are governed by the contract which provides for alternative dispute resolution by way of arbitration. When the parties have consciously agreed that the matter be referred to the Arbitration, this Court is of the view that it cannot be said that MSEF Council has no jurisdiction at all, no doubt, if the MSEF Council had entertained the claim based on works contract and passed an order, it may be easily said that it lacks jurisdiction, whereas the MSEF Council has just with the consent of the parties referred the matter to arbitration and an Arbitrator has also been appointed, wherein, also no objection has been raised by the petitioner. Therefore the above judgment of the Andra Pradesh High Court will not be helpful to the petitioner.

 

  1. The learned counsel for the petitioner also relied upon the judgment of the Hon’ble Supreme Court in Kerala State Electricity Board Vs. Kurien E.Kalathil reported in (2018) 4 SCC 793. The Hon’ble Supreme Court has held that insofar reference of the parties to arbitration, oral consent given by the counsel without a written memo of instructions does not fulfill the requirement under Section 89 C.P.C. Since referring the parties to arbitration has serious consequences of taking them away from the stream of Civil Courts and subject them to the rigor of arbitration proceedings, in the absence of arbitration agreement, the Court can refer them to arbitration only with written consent of parties either by way of joint memo or joint application; more so, when government or statutory body like the appellant-Board is involved. In the above judgment the Hon’ble Apex Court has clearly spelt out that in the absence of any written instructions either by way of memo or joint application, the matter cannot be referred to arbitration. Admittedly, in this case, the parties agreed for referring the dispute to arbitration in the contract itself. Besides, the petitioner has also given consent for referring the matter to the Arbitrator. No objection has been raised by the petitioner. Therefore, the above judgment is also not applicable to the facts of the present case since the contract between the parties itself provides for reference to Arbitration. The petitioner has consented to refer the matter to arbitration and without raising any objections participated in the arbitration proceedings and now the arbitration is in the final stages and therefore now the petitioner cannot be permitted to approbate and reprobate.

 

  1. The Hon’ble Apex Court in R.N.Gosain Vs. Yashpal Dhir, reported in AIR 1993 SC 352 has observed as follows:

“Law does not permit a person to both approbate and reprobate. This principle is based on the doctrine of election which postulates that no party can accept and reject the same instrument and that “a person cannot say at one time that a transaction is valid any thereby obtain some advantage, to which he could only be entitled on the footing that it is valid, and then turn round and say it is void for the purpose of securing some other advantage.”

  1. Such view of the matter, this Court is of the view that as the dispute itself is not resolved by MSEF Council, only the matter has been referred to Arbitration with the consent of the parties, further the contract governing the parties also provides for such reference to arbitration, the second respondent has also already invoked the Arbitration Clause by issuing notice in the year 2013 itself and the petitioner has also participated in the said arbitration proceedings, now the petitioner cannot challenge the impugned order at this belated stage that to when the arbitration proceedings is in the final stage. Further, when the parties have consciously agreed to resolve the dispute arising out of the contract by way of arbitration, they can very well agitate their right before the Arbitrator and canvass their points and no prejudice would be caused to them since the Arbitrator has been independently appointed by the Arbitration Center of the Madras High Court.

 

  1. Such view of the matter, this Court finds no merit in this writ petition and the writ petition is liable to be dismissed and accordingly dismissed. Consequently, the connected miscellaneous petition is closed. No costs.

03.01.2023

Index : Yes / No

Neutral Citation : Yes / No

kk

 

To

 

  1. The Chairman,

Micro Small Enterprises Facilitation Council,

Represented by its Regional Joint Director of

Industries and Commerce,

Thiru-vi-ka Industrial Estate,

Guindy, Chennai – 600 032.

 

  1. The Hon’ble Presiding Arbitrator,

Madras High Court Arbitration Centre,

High Court, Parry’s Corner,

George Town, Chennai – 600 108.

N.SATHISH KUMAR, J.

 

kk

 

 

 

 

 

 

 

 

 

 

 


W.P.No.6216 of 2021 and

W.M.P.No.6834 of 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

 

03.01.2023

 

You may also like...